Grieve Project Update
Sydney, Sep 27, 2017 AEST (ABN Newswire) - Elk Petroleum Limited (
ASX:ELK) (
EKPTF:OTCMKTS) provide the Grieve Project Update presentation with construction well advanced heading into Autumn.
Grieve Field Development
Heading into the final phases of field development
- Offsite fabrication activities nearing full completion
- Final deliveries of pipe works expected early October
- On-Site construction highly advanced
- Installation of all major process equipment 100% complete
- Process Building mechanical construction & pipe works 100% complete
- Building erection highly advanced making facilities weather tight to complete construction
- Well construction work -workovers & completions nearly complete
- Field fully repressurizedto preproduction maximum
- Project completion, production start-up guidance remains unchanged -late CY2017/early 2018
To view the presentation, please visit:
http://abnnewswire.net/lnk/BT9IEKWW
About Elk Petroleum Limited
Elk Petroleum Limited (ASX:ELK) (OTCMKTS:EKPTF) is an oil and gas company specialising in Enhanced Oil Recovery (EOR), with assets located in one of the richest onshore oil regions of the USA, the Rocky Mountains. Elk's strategy is focused on applying proven EOR technologies to mature oil fields, which significantly de-risks the Company’s strategy of finding and exploiting oil field reserves.