Adelaide, Mar 1, 2013 AEST (ABN Newswire) - Toro Energy Limited (
ASX:TOE) announce the half yearly report with key events over the period and up to the date of the report including;
- Western Australian Minister for Environment's decision to approve the Wiluna Uranium Project;
- Maiden inferred uranium resource for Theseus Deposit;
- Timeframe for Federal Environmental decisions, for the Wiluna Uranium Project, extended to 31 March 2013;
- Engineering design and costing phase of the DFS delayed until after Federal Environmental decisions made;
- Managing Director transition;
- Completion of A$12m convertible debt facility with Macquarie Bank Ltd.